×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

(OP)
Seriously, I hope I'm in a wrong thread, and I really need a quick answers here, hopefully you guys can help me on here. So what are the advantages & disadvantages if we pouring the concrete beam-slabs monolithic with concrete colomn? Like we pour the concrete beam-slab right after we done poured the concrete colomn?

RE: Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

I can’t think of any significant advantages of going with a monolithic pour. I guess you would eliminate a non-critical shear friction joint and perhaps improve water tightness? I would think that constructability would suffer with a monolithic pour.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.

RE: Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

It would be pretty tough to pour a column with all the beam rebar in place. You need a good 4" to 6" opening to fit in the chute.

When I am working on a problem, I never think about beauty but when I have finished, if the solution is not beautiful, I know it is wrong.

-R. Buckminster Fuller

RE: Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

The main disadvantage is that the column will shrink, causing cracks under the beam-slabs. It is definitely not recommended.

BA

RE: Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

BA is correct, but I think it is more accurate to say that the plastic concrete in the column will settle, while the beam concrete will be held up by the reinforcing. A crack at the junction develops, which is obviously not good. This subject has been discussed here before, and the answer is always the same.

RE: Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

(OP)
Thank you guys for the comments. I was thinking the same as well, but the construction project that I was internship-ed did all the job in one day even without waiting the column to be harden. When I asked the 'higher' people there, they said because they got a very short time schedule, so that why they did that. And as the result there are some columns that shrink at the end.

RE: Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column


As one who has designed a substantial amount of shoring/falsework/formwork, I feel compelled to comment on this.

BAretired hits on one disadvantage, the column concrete will shrink. If the shoring supporting the beam/slab is stiff enough, there will be some concern regarding cracking. ACI does address this issue and recommends a delay in the placement of the slab/beam concrete after completing the column concrete placement.

My main concern is lateral stability of the entire formwork & falsework system. The entire system must be designed for the potential and required lateral loads (2% of the dead load or 100 lb/lineal ft). When the columns are placed a couple days before the slab/beam is placed, one gains some stiffness to resist lateral loads (by edge bearing of the deck plywood against the sides of the columns).

This is a common situation in NYC mid-rise projects. The column & wall concrete is often placed after the deck formwork has been installed. Generally there is a delay in the deck concrete placement.

I do know that because of the column concrete shrinkage, the forms used for the columns can become 'locked' into place. This can result in having to destroy (or damage) the forms in order to remove them.

Ralph
Structures Consulting
Northeast USA

RE: Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

I'll admit, as a concrete contractor I have done both. I will reinforce that even in a 2 day cycle, the concrete columns are poured the day before. Not only does it benefit the structure (in terms of shrinkage as BA mentioned) to place the columns the day before, it also makes the process more efficient as the concrete deck placement starts right in the morning, opposed to waiting until the columns and shear wall to be filled.

RE: Advantages & Disadvantages of Pouring Concrete Beam-Slabs Monolithic with Concrete Column

To the best of my knowledge, there are no advantages beyond "time", which I think can be shown to be a false savings, when pouring monolithically.

It is always a mistake, and principally poor pour practice, pal.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources