INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

In-Channel Concrete Sediment Trap

In-Channel Concrete Sediment Trap

In-Channel Concrete Sediment Trap

(OP)
We have roadside concrete stromwater channels and are looking to put a sediment trap within the channel. Has anyone ever seen this done befoe? I would imagine it would be a concrete box structure with a grate that would just need regular maintence. Probably a 4" drain pipe in the bottom of it.

RE: In-Channel Concrete Sediment Trap

Interesting. Not sure how well that would work. I presume you would size the channel for a 10-year event or greater and the sediment traps for a smaller storm (1-2 year). I envision that once the vault fills up with water no more sediment would be collected; sediment would bypass the vault entrance with the discharge. One would have to size the vault system to collect the entire design storm flow to allow for sedimentation. How large would the vault have to be to settle out the sediment. When designing a settling basin the detention time is the key for settling out the sediment particles. These basins are rather large; 1/2-ac plus for the last one I designed. It will be interesting what other folks say.

RE: In-Channel Concrete Sediment Trap

How about some rock check dams in the channel? Or removing the concrete lining all together and letting nature do it's thing.

RE: In-Channel Concrete Sediment Trap

Rock check dams would slow down the flow but would not trap fine sediment. It takes days (not minutes) to get sediment to significantly be reduced. I have used 72 hours in the past but this does little towards a 48 hour drain time requirement. Storm water, I have been told, should not be retained longer than 48 hours for quantity measures but should be retained at least 72 hours for qualitative measures. It is impossible to do both.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources