INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Additional longitudinal weld joint in a pressure vessel shell of ID 1300mm

Additional longitudinal weld joint in a pressure vessel shell of ID 1300mm

Additional longitudinal weld joint in a pressure vessel shell of ID 1300mm

(OP)
A pressure Vessel which is designed as per ASME SEC VIII Div1, shell segment ( two out of four segments) ID 1300mm and thickness 16mm (material SA 516-70) is made with two longitudinal weld joints as against drawing requirement of one to save material.The joints are separated by 30 deg and is not fouling with any of nozzles.The vessel calls for spot Radiography.Is the additional weld joint also to be spot radiographed or 100%.Is it required to take client permission for this deviation ( Drawing is not approved by client)
Sivaramakrishna Rao.Y

RE: Additional longitudinal weld joint in a pressure vessel shell of ID 1300mm

srk127, while (IMO) kind af a poor practice in a vessel this size, it is permitted.

Extents of spot RT is per UW-52. Likely no additional RT is required.

Don't know what else your contract might require, but if drawing approval is not required, you are most likely good to proceed.

HOWEVER, I doubt your client is expecting two long seams on a 1300mm (~ 51 inch) cylinder. As a customer relations matter you might want to get their buy-in.

Regards,

Mike

RE: Additional longitudinal weld joint in a pressure vessel shell of ID 1300mm

Because the as-delivered pressure vessel was not built "per-plan" you should Xray (RT exam) both of the full seams. Once a plan is willingly deviated from by the fabricator without your knowledge, you do not know what else was not completed correctly.

And, go ahead a charge the fabricator for the RT time and money. After all, he is the one saving himself time and money at your reputation and expense.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources