Adding a Hoist
Adding a Hoist
(OP)
We are adding a hoist to a larage open steel structure (industrial) on higher elevation/floor. Do I need to check all beams, columns and connections?
To how far checks need to be done the hoist is 1Ton capcity.
Thanks
To how far checks need to be done the hoist is 1Ton capcity.
Thanks






RE: Adding a Hoist
That doesn't necessarily mean you have to run detailed calculations on each member and connection, but it might.
I'm normally not bold enough to say this but I'm having a rather difficult day so today I'll be the arsehole, that is a very basic question should you be tackling the project if you can't answer something so rudementary?
Now that I'm back off my high horse, if the existing structure was designed and built in house it may not meet any specific code and as such could cause unforeseen issues. Follow the load down to the foundation and check items as required.
RE: Adding a Hoist
I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.
RE: Adding a Hoist
If you have a structural model or previous calculations showing the utilization ratios for the existing structure, this should give you a better idea of the impact from the 1 ton hoist. If the beams and columns are only at 60%, it probably won't make a difference.
Usually the industrial structures are designed conservatively and I can't see a 1 ton hoist failing the structure.
I would check all beams and connections that will see the increased loading first. Use engineering judgement after that.