INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Pressure Vessel and Heat Exchanger External Bolting Material Selection

Pressure Vessel and Heat Exchanger External Bolting Material Selection

Pressure Vessel and Heat Exchanger External Bolting Material Selection

(OP)
Dear group members,

I am little confused about following question on external bolting selection for girth flange (w.r.t to flange material / sour service / temperature / Allowable stress and Flange design)

1.Currently we are using SA 193 B6 bolt (13%Cr S41000) for SA 182 Gr.F6a (13%Cr S41000) Flanges to match bolt material with flange material for high pressure (320 bar), Carbon Dioxide (CO2) service electric heaters.
Due to high pressure bolt size is coming very high (3" to 4") and equipment is in sour service so hardness can be the issue to comply NACE MR0175 hardness requirement.
Please highlight any issues face in past with B6 material and what alternative bolt material can be use.
2.General practise is to use LAS bolting with SS flange however in which case we need to go for SS bolting for SS flanges??
3.In case of using alloy steel bolting with Stainless Steel Flanges, What are the hidden problems like galvanic corrosion and differential thermal expansion??
4.What are other problems of going with SS bolting??
5.For stainless steel bolting, Which are acceptable bolting material grade grades as per NACE MR0175 as NACE does not specify the acceptable grades for SS bolting like B7M and L7M is specified in part-2.

Please share your views.

RE: Pressure Vessel and Heat Exchanger External Bolting Material Selection

For process piping design, the evaluation of bolting materials depends on the following;

1. Selection of the applicable piping code.

2. Piping code bolting material. The reason for using bolting material listed in the piping code is to provide quantifiable allowable stress values and maximum and/or minimum allowable use temperatures in design.

3. Narrowing down the bolting material options in the piping code requires detailed engineering evaluation of the specific service environment; external exposure and internal process fluid, range of service temperature, corrosion exposure(general, galvanic and/or crevice), thermal expansion exposure and affect on bolt preload, NACE compliance, if applicable, material cost and availability.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.