×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Code question: installer

Code question: installer

Code question: installer

(OP)
Given that an installer is installing pressure-rated code-stamped vessels manufactured by a different fabricator who is a code shop, and given that the installer will only be welding interconnecting piping, and its elbows, tees and flanges, and his other work will be the installation of valves and instrumentation...

...must the installer be a "code shop" if the system will be under pressures greater than 15 psig, and ... what's the reference to back this up?

RE: Code question: installer

The installer should comply with ASME B31.3.

Good luck,
Latexman

Technically, the glass is always full - 1/2 air and 1/2 water.

RE: Code question: installer

or the equivalent Code local to you.

Good luck,
Latexman

Technically, the glass is always full - 1/2 air and 1/2 water.

RE: Code question: installer

(OP)
Yup, that was my understanding. Thanks!

RE: Code question: installer

(OP)
One more question...

... is the R stamp required to weld piping? I do not think so but I do not know.

Thanks for be so helpful!!!

RE: Code question: installer

(OP)
Got it from another source... R stamp is not required since not welding on the vessels.

RE: Code question: installer

Depends on your jurisdiction. Compliance with B31.3 is minimally necessary- ASME IX welders and procedures, NDE per code etc. But in some jurisdictions such as Ontario, Canada, you are ALSO required to have a Certificate of Authorization from the "authority having jurisdiction" (AHJ), and to complete a form with them acting essentially as AI to certify that the hydrotest and other NDE are completed. Your own situation may vary.

RE: Code question: installer

It also depends upon the vessel in question. If you have an ASME section VIII vessel no field stamp is required and the above recommendations should be followed. If you have a section I boiler, then the field fabricator must be certified to that code.

Boilers are required to be fabricated to a more regulated standard. In the US, each state will often have its requirements for installation and issuing operational permits.

A "good" field fabrication contractor should (in theory) know all the above.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources