INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

foamed-concrete

foamed-concrete

foamed-concrete

(OP)
hi. i am designing two floor steel factory. At mezanine floor using composite beam with 8 cm concrete. And planing to put energy panels at roof. i have several questions.

1. Roof has a %2 slope. starts with 7.5 meters and finishes at 8.00 meter. How can we use rigid diaphragm? ETABS warning is you cant create rigid diaphragm at different levels.
2. Can we use foamed-concrete over metal-deck? In turkey there is foamed concrete with 1 MPa strength and 400kg/m3 density. I think it is strength enough to make a rigid diaphragm. I am wondering is there any construction abroad using this material over metal-deck. I searched from internet, generally there is lightweight concrete with 1600 kg/m3 density and high strength.

RE: foamed-concrete

In fact you can, you just have to define a story at 7.50 m height and another one at 8m, place the slab and just add it to a diaphragm.

Yes you can place concrete on top of a metal deck, just go to the define frame sections options and define a metal deck according to your specs. Metal deck alone is allowed by the ASCE in low rise buildings to be modeled as a Rigid diaphragm assuming it complies with the certain limitations (Chapter 26- General wind loading).

RE: foamed-concrete

(OP)
But when i modeled the roof with composite beam with concrete after composite beam analysis; at composite beam design menu i am looking to the reports and it says my cover N/A, dont see my metal deck options there. I think because of the roof's %2 slope program dont realize it as a composite beam or i am doing something wrong. And when i add a slab from 7.5 height to 8; ETABS warning is can create rigid diaphragm at different Z levels. Then i defined rigid diaphragm from shell objects and i think problem solved.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources