ASME SECII MTR REQUIREMENTS TO BE VERIFIED
ASME SECII MTR REQUIREMENTS TO BE VERIFIED
(OP)
What are the requirements that must be verified on an MTR prior to releasing to fabrication?
I was told to look at chemical composition only but what about Elongation, Hardness etc. I would think that must be done as well.
I was told to look at chemical composition only but what about Elongation, Hardness etc. I would think that must be done as well.





RE: ASME SECII MTR REQUIREMENTS TO BE VERIFIED
RE: ASME SECII MTR REQUIREMENTS TO BE VERIFIED
These specs will each have a list of required characteristics and tests.
The MTR should reference the Code and specs as well as provide verification o fall required tests.
= = = = = = = = = = = = = = = = = = = =
Plymouth Tube
RE: ASME SECII MTR REQUIREMENTS TO BE VERIFIED
If the material is for Pressure vessel ASME Sec VIII Div 1, then start at UG 94 and go to other clauses from there after you have exhaused all the links, go to UG-10, it will take you to many placed. when you are finished with all the links, you will have reasonable idea.