Import meter bill
Import meter bill
(OP)
I am working in 125 MW Diesel Powered IPP connected to 132 KV grid through 3 transformers of 63 MVA each indepedently connected to 3 engines each at each transformer and exporting to common bus .
when dispatches are low ,i am registering import bill as other transformer are not closed.When i close transfomer to avoid losses high inrush is affecting transformer.How to avoid import billing.I feel practice of frequent switching off and cannot be recommended.Can someone give a solution
Khatoon
when dispatches are low ,i am registering import bill as other transformer are not closed.When i close transfomer to avoid losses high inrush is affecting transformer.How to avoid import billing.I feel practice of frequent switching off and cannot be recommended.Can someone give a solution
Khatoon






RE: Import meter bill
A company I worked for had interconnections with wind farms, and we did charge them for power when they were not generating. It's a cost of doing business. You buy power from the utility you are connected to when you are not generating, because it is cheaper than running your generation to serve only your station power.
My answer is look at the alternitives, and do the math, to find out which really is cheaper.
RE: Import meter bill
Presently I am in USA for visit
Thanks
khatoon