INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

ASME B31.3 X-Ray REQ

ASME B31.3 X-Ray REQ

ASME B31.3 X-Ray REQ

(OP)
As a manufacturer of piping under ASME 31.3, what are the requirements of X-ray?
Does the manufacturer have to keep the X-ray film, is there anything that states that?

RE: ASME B31.3 X-Ray REQ

I assume that you are referring to the manufacturer of longitudinal or spiral seam welded pipe. The ASTM, API or Purchaser specifications' requirements govern and B31.3 does not address a time frame.

RE: ASME B31.3 X-Ray REQ

(OP)
We are performing round seam welds on Butt joints, it is a spool, customer asked for the 5% Random.
They have always asked for the film, but are we required by code to keep a film for our records,or will the Reader sheet be sufficient?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources