×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Overpressured during Hydrotest of boiler

Overpressured during Hydrotest of boiler

Overpressured during Hydrotest of boiler

(OP)
After 1 nos of boiler superheater tube replacement, we conducted hydrotest. the test pressure is 1.5 x MAWP= 71 Bar. But due to mistake in chart recorder, we overpressured it till 122 bar.

We depressured it and performed visual inspection to see if the overpressure caused any deformation. But there was non found. So we redo the hydrotest with correct test pressure of 71 bar, and we found that 1nos of tube (different from the 1 we replaced) is leaking at the superheater header to tube weldment.

My question is, could the tube leak due to the overpressure or the tube is already defect before that. Is there a way to know what caused the tube leak. The original tube we replaced also because of the defect in the weldment.
All the other tubes are fine with no trace of leak at 71bar.

Thank you

RE: Overpressured during Hydrotest of boiler

I have trouble believng that the low temperature components ( whose allowable stress is a fraction of yield or UTS) had been overpressured to 2.57 times allowable stress . In particular any pressure vessel or flange or forged valve would have experienced some failure at 1.25 times allowable .

"Whom the gods would destroy, they first make mad "

RE: Overpressured during Hydrotest of boiler

I could accept the single-case over-pressure incident with a burst (complete failure) of the assembly, and in truth, the writer did admit there was the single failure. We really do "over-design" and "under stress" components sometimes with our choices. And, sometimes, the tolerances and cooler metal (higher stress resistance) and slow pressurization rate and wall tolerances and weld strengths do all add up on the "stronger than expected" side.

But I am surprised there was no noticeable deformation or stretching or ballooning of components, particularly those with the larger diameters. Do your inspection again looking not at the small diameter tubes, but the large diameter headers and pipes.

RE: Overpressured during Hydrotest of boiler

I do not believe the test at higher pressure rupture the welds, it may have been already crack or traces. but it looks that you wish a scape that the owner will not accept...

RE: Overpressured during Hydrotest of boiler

You mentioned that this is a boiler and if so then the rules for pressure vessels don't apply. If built to the ASME Code then this is a Sec. 1 boiler and per PG-99.1 "No part of the boiler shall be subjected to a general membrane stress greater than 90% of its yield strength ...". This is what you need to ensure has not been exceeded otherwise you have a piece of scrap.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources