INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Machine Tool Load Limit on 6th Floor

Machine Tool Load Limit on 6th Floor

Machine Tool Load Limit on 6th Floor

(OP)
We are an OEM of x-ray equipment. Our end-user has a 6th floor load limit of 3KN/m2. I know that this calculates to 62.66 lbs/ft2. I have two machines that I need to determine whether or not they fall inside or outside this limit. Machine A: System weight = 2000 lbs with a base that measures 30" x 30" with a leveling foot of 3.5" dia on each of the 4 corners. Machine B: System weight = 2500 lbs with a base that measures 32" x 40" with a leveling foot of 3.5" dia on each of the 4 corners. The systems will be bolted in position. Appreciate any assistance.

RE: Machine Tool Load Limit on 6th Floor

Sounds like you need to hire a structural engineer.

Maine EIT, Civil/Structural.

RE: Machine Tool Load Limit on 6th Floor

you have a load limit in units force over area. you know the weight of the equipment. you know the area it occupies. so what is its equivalent area load? a simple calculation that should give you some idea if the floor can handle the equipment...

Something else to consider may be vibration limits for the machinery - something that may require an in depth structural analysis of the floor in question beyond what load it can handle.

It points back to TehMightyEngineer's comment - hire a structural engineer.

RE: Machine Tool Load Limit on 6th Floor

Your machines are more like concentrated loads than evenly distributed loads. The floor needs to be checked for these concentrated loads...by a structural engineer.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources