INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Effect of mixing exist base material and high PI subgrade and Lime Stabilizing

Effect of mixing exist base material and high PI subgrade and Lime Stabilizing

Effect of mixing exist base material and high PI subgrade and Lime Stabilizing

(OP)
I am rebuilding an old road in Texas. The proposed section is 1.5" type'D' Hmac over 2.0" Type 'B' HMAC over 8.0" A2Base, over 6" lime stabilized subgrade. The existing road section was thicker than the proposed because of 9-inches of existing asphalt.

What would be the effect of mixing 2-inches of base material with 4 inches of high PI natural subgrade and lime stabilizing it?

Would this subgrade section have about the same structural number as 6 inches of lime stabilized high PI natural subgrade?

thanks in advance for your support.

RE: Effect of mixing exist base material and high PI subgrade and Lime Stabilizing

ChipperB...those are questions that can really only be answered by lab testing.

Considering your existing pavement section, have you thought about mixed in-place recycling? You could do a 10 or 12 inch depth mix and make a very stable base for an asphalt surface. This would likely be very cost effective for your client. Check it out.

RE: Effect of mixing exist base material and high PI subgrade and Lime Stabilizing

I'm assuming that would translate from TexDOT-speak into 1 1/2" top course HMA on 2" base or binder, over 8" granular subbase. That's a pretty light section. What are your traffic loads in ESALs?

I agree with Ron on the both the need for lab tests and the effectiveness of full-depth reclamation.

RE: Effect of mixing exist base material and high PI subgrade and Lime Stabilizing

Agree with the full-depth reclamation option. 9" is a lot of asphalt - seems like a waste to not use it.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources