INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Sonotube Foundation Construction

Sonotube Foundation Construction

Sonotube Foundation Construction

(OP)
What is the proper way of constructing a round concrete pier foundation where the top is above grade, like for a small light pole foundation? My primary concern is the lateral resistance of the foundation. My understanding is these types of foundations are normally constructed by auguring a hole (say it's 4' deep), and forming with a sonotube. I assume the sonotube would only be used to form the portion of the pier above grade, so you're casting against undisturbed soil... or is it really "undisturbed" when you use an auger? Even after augering, it's probably necessary to clean up the hole of loose soil, and consolidate the bottom in some manner. If you were writing notes for the proper procedure on your drawings, what would you include, or should the structural engineer not dictate means and methods? I want to make sure I have the lateral resistance required.

RE: Sonotube Foundation Construction

Besides cleaning out loose dirt, we usually don't require much preparation. And I suspect thae contractor doesn't do a good job of that. The sides are considered undisturbed.
I've designed a bunch of these. Between the mass of the concrete and the lateral resistance of the soil, never had an issue.
Think of it this way; You have a 5" x 5" 12 gage aluminum pole. You have a two or three foot diameter piece of reinforced concrete 4'-0" long. What's going to fail first?

RE: Sonotube Foundation Construction

ASABE EP486 Shallow Post and Pier Design. This reference will help.

RE: Sonotube Foundation Construction

The sonotube is used for looks at and above grade. You rely on the concrete being placed directly against the soil in the working part below grade.

Michael.
"Science adjusts its views based on what's observed. Faith is the denial of observation so that belief can be preserved." ~ Tim Minchin

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources