Concrete placement for elevated slab
Concrete placement for elevated slab
(OP)
Contractor would like to place concrete for a 5" elevated slab on composite decking. The base plates for the steel columns supporting the slab have been grouted underneath however the 12" depth blockout around the columns have not been poured with concrete. All the anchor bolts for the columns are in a 2' footing and have been tested and approved. Bracing for the exterior tilt walls is still in place. Is there anything that would prevent the contractor from placing concrete on the elevated slab?
I am use to having the blockouts infilled prior to placing concrete on an elevated slab however the contractor stated with the bracing in place he does not have to place concrete around the columns base prior to placing concrete on the elevated slab. Any thoughts?
I am use to having the blockouts infilled prior to placing concrete on an elevated slab however the contractor stated with the bracing in place he does not have to place concrete around the columns base prior to placing concrete on the elevated slab. Any thoughts?






RE: Concrete placement for elevated slab
RE: Concrete placement for elevated slab