INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Pavement Subgrade Problem

Pavement Subgrade Problem

Pavement Subgrade Problem

(OP)
I need to remove some old fill and replace it under a road adjacent to an abutment for a one lane bridge. I want to start at the abutment and excavate in 4 foot-long sections so that if an emergency vehicle needs to use the road, it could be filled "rapidly" and some 4'x8' steel plates could be placed on top to let the vehicle pass.

Could I use rip-rap (specs?) for emergency fill and then use a mixture of rip-rap, crushed stone (specs?) and flowable fill (2500 psi) for my permanent fill? I plan to excavate 3' deep (minimum) to as much as 5'. Once the flowable fill cured for (?) days, another 4' long section would be opened up. I will need to do this for about 12'-16' on each side of the bridge.

I am planning to use concrete pavement on top. The pavement is asphalt now.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.