INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

2-D Lateral Earth Pressures on Stepped/Tiered Sheet Pile Walls

2-D Lateral Earth Pressures on Stepped/Tiered Sheet Pile Walls

2-D Lateral Earth Pressures on Stepped/Tiered Sheet Pile Walls

(OP)
Please see the attached sketch as this may get confusing...

I have a sheetpile wall (SP-1) behind an existing bridge abutment wing and beyond. Behind the wing, I'm relying on the the wing to act as a waler for SP-1 per my very experienced bosses recommendation). Beyond the wing SP-1 is a 15ft tall cantilevered wall. To get to the top of the drilled shaft elevation (D.S.) for construction, we're installing a short 3ft tall wall (SP-2) perpendicular to SP-1.

Question 1 - How do I consider the lateral earth pressure effects on SP-2 from SP-1? One of my supervisors has told me that the passive resistance in front of SP-1 will create an increase in active pressure behind SP-2 but he can't find his reference for guidance on how to quantify it. We believe its related to poisson's effects.

Question 2 - at the dredge line of SP-2 in front of the wingwall there will be interaction between the passive pressures in front of SP-2 and SP-1. How do I quantify that? I was thinking use a reduced Kp for each wall that has a resultant Kp equal to that of the soil.

Thanks for the help.

-rmf338

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources