Industrial engineering common times
Industrial engineering common times
(OP)
I need to know if there are tables available that show how long the average human being takes to perform a certain task. Specifically, I need to know how long it takes someone to install 5 nuts and washers to a threaded stud. We perform time studies at my company, but we are looking to standardize times for certain elements across the company. I need to know if there are published industrial engineering standards that list times for tasks that are common to a manufacturing facility.





RE: Industrial engineering common times
Reaching for a part is 16 TMU's
Grabing a part 3 TMU's
and so on. When you split whole procedure, define it with times for each, then add some time for other factors (multply with 1.3854, i think :) ). This time is the real time for making this job.
Also on Net there are avilable software that do this for you (TiCon, ProCon etc.)
RE: Industrial engineering common times
MTM or Work Factor. It is a very simple exercise. Any
pick up and place with one hand takes about .05 min. There are MTM tables that you can use. The same goes for Work Factor. Work Factor uses larger units of measurement and for me was a lot easier to use. Both are good.
RE: Industrial engineering common times
RE: Industrial engineering common times