INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

RCP to Existing Junction Chamber

RCP to Existing Junction Chamber

RCP to Existing Junction Chamber

(OP)
What does the connection of a new RCP to an existing Junction Chamber look like?
This would be a situation where a new hole is cut into the existing Junction chamber and the new 72" RCP connected to the junction chamber (about 16'x16').

Sorry if this is basic but I'm just trying to understand what this typical detail looks like. Even for new construction.

Thanks

EIT
www.HowToEngineer.com

RE: RCP to Existing Junction Chamber

I would say the outside diameter of the RCP (7.16', "B" Wall) is too large to not evaluate the chamber wall for the structural integrity. Without alot of detail the hole needed for the connection will interupt too much reinforcing steel on the chamber. I would have a structural engineer evaluate the best approach.

RE: RCP to Existing Junction Chamber

Typically, the opening is around the pipe is closed up with bricks. I would suggest grouting a cradle below the pipe rather than trying to brick it up.

RE: RCP to Existing Junction Chamber

never heard of "bricking", we use a concrete collar, usually reinforced for something this large or even for small pipes. depends on the design and loading on the structure. structural engineer is recommended

RE: RCP to Existing Junction Chamber

(OP)
Thanks for the input.

I'm trying to understand what the typical connection looks like between the pipe and the wall of the chamber for a retrofit condition or even new construction. Is there typicall just grout between the pipe and the wall or is there some other sort of connection with usually ties the two together?

EIT
www.HowToEngineer.com

RE: RCP to Existing Junction Chamber

RF -Take a look at the attach. It's a NYCDEP standard sheet for new pipe installation in a new catch basin. Typically on NYCDOT or NYSDOT projects a 3" annular space is left around the pipe (although sometimes we have to deal with larger openings), then it's grouted or bricked after the pipe is installed. The pipe is placed flush with the inside face of wall. Bricks, conforming to ASTM C936, are the most common way of sealing the gap.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources