design of a digester tank
design of a digester tank
(OP)
Hello
i am designing a tank in order to be used for as a digester, i can't yet decide which standard to use (API 650, API620 ...) I can't decide because i don't know the pressue that lies within my tank, should it exceed 15 psig, what standard should i use , and the design of the tank must be vertical an abouveground according to my client,
it would be helpful to indicate the pressure underwhich, the biogaz must be released aout of the tank
thank you in advance
i am designing a tank in order to be used for as a digester, i can't yet decide which standard to use (API 650, API620 ...) I can't decide because i don't know the pressue that lies within my tank, should it exceed 15 psig, what standard should i use , and the design of the tank must be vertical an abouveground according to my client,
it would be helpful to indicate the pressure underwhich, the biogaz must be released aout of the tank
thank you in advance





RE: design of a digester tank
Should you not be consulting a biological / chemical engineer so as to determine the optimum pressure and temperature for the process under consideration, based on material being digested, type of biological process being used, desired gas production rate, raw material feed rate, sludge removal rate, whether there will internal agitation of the slurry or if straight gravitational top-down flow is to be employed, etc., etc.?
Once you have this information you will be in a much better position to develop a successful design.
CR
RE: design of a digester tank
Question:
* should these data be handed to me (as a mechanical engineer) by a process engineer or should i try to understand how digester works and design it according to my calculations ?
RE: design of a digester tank
For most digesters I have seen you don't need a chemical engineer to design, but someone with experience in the field. I don't know what you plan to do, so I can't advise you further.
RE: design of a digester tank
In fact, i have been given the data sheet for the design of a vertical tank indicating an overpressure of 5 bar, i couldn't decide which standard to use since API 620 are only for tanks with a maximum overpressure of 15 PSI (2.03 bar).
An exemple of the tank design woold be also very informative
i'm really looking forward to receiving your reply
RE: design of a digester tank
- Throughput (lbs/day, GPD) (what flow needs to be handled?)
- Biological Oxygen Demand of the feedstock
- Makeup of feedstock (industrial? Municipal)
- Desired solids retention time (days)
RE: design of a digester tank
-the diameter of the tank is suppose to be 15m, this information may give an idea about the tank size, and the flow to be handled.
-i don't understand the second question.
-Municipal
-30 days approximately
it would be very helpful to indicate the bio-gas release out of the tank.
i am looking forward to receiving your answer
RE: design of a digester tank
We understand correctly that you do the mechanical design of a steel tank and that it's the first time you do this for this process? Do you need to design the tank only, or also equipment (mixer, piping, heating ...)? Do you know what is requested in terms of manholes, portholes? Insulation?
Do you size the tank? Do you define the pressure you require (15psig is still what you aim for?)?
MAybe I'm wrong, but I feel you should straighten out with your collegues who does what (process design, equipment specification, tank design) because maybe that's not totally clear.
Maybe look at one of your competitors that do a lot of digesters:
http://www.glstanks.com/en/index.php
RE: design of a digester tank
to answer your questions:
- i only need to design the tank (no mixers, no heater), but knowing the overall of the process could only better my work
-as far as the tank size is concerned, i am doing a design for various kind of shapes (dome roof, cone roof) and sizes (exemple:diameter=15m).
- the pressure was only chosen (less than 15 PSIG) so the standard API 620 could be used for the design.
- you were right, i have recently contacted the process engineers and things are going better now.
thank you for your responds and i will keep this thread open in case i need any more help.