INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Stored Energy in Pneumatic Pressure Test

Stored Energy in Pneumatic Pressure Test

Stored Energy in Pneumatic Pressure Test

(OP)
Hi everyone,

I'm joining the team now with, I hope, an interesting question:
Is there a real limit for stored energy during pneumatic pressure test?
I'm dealing in these days with the Client, in France, in a LNG terminal Receiving.
EN Codes are far from a real answer and obviously we're using, as reference, the good and always actual ASME PCC-2.
May I have a suggestion?

RE: Stored Energy in Pneumatic Pressure Test

We had a lively discussion recently: http://www.eng-tips.com/viewthread.cfm?qid=358563

To address your specific concern; nope, no 'limit' to stored energy. Use the 'Good Engineering Practices' delineated in the post to control the risk. And when you designate your exclusion zone, have it patroled. There is always some idiot that thinks that your piddly test is nothing for him/her to respect. And spend as little time at 'overload' as necessary. ASME says '10-minutes', then reduce pressure and closely inspect the item. On my tests, 10-minutes goes pretty fast [if it made it 30-40 seconds, the remaining 9 minutes seems a little unnecessary]. Once the pressure has been dropped down towards Design, from the full test pressure, you are in 'safe territory' and can reasonably assume that your item has proven itself to be safe. Start checking for pinhole leaks, and allow everybody back into the area.

RE: Stored Energy in Pneumatic Pressure Test

(OP)
Thanks Duwe6,

I did, at least 500-600 pneu test and I know the risk involved.
I'm just looking for answers regarding the limit...
On my last job I was permitted to reach 862 MJoules, not bad eh?
Following ASME PCC-2, now, with that limit, the safety distance is set about 120 meters....
My client insists that the max shall be 135,5 MJoules...

RE: Stored Energy in Pneumatic Pressure Test

And they arrived at that number how?? 10MJ in a 'cheezy' vessel is a LOT riskier than 800MJ in an ASME vessel with Full Radiography. Arbitrary limits are just that -- arbitrary.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources