INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Temporary fence for falling debris

Temporary fence for falling debris

Temporary fence for falling debris

(OP)
I have a situation where a 100 year old building has a brick facade which has severely deteriorated and is imminently hazardous. I need to provide a repair plan to the city. In the interim I would like to recommend a temporary fence to restrict access. Is anyone aware of how car the fence should be offset from the building? The building is 90 feet tall and my concern is that debris from the top floor could land on the public side of the fence.

RE: Temporary fence for falling debris

No answer, but some questions: Are there any projections in the walls, perhaps window sills, or trees which would cause falling objects to be diverted out. Also, what is on the ground to possibly cause bounced objects to be directed out.

Any sidewalks beyond possibly requiring a temporary roof protection to pedestrians.

RE: Temporary fence for falling debris

(OP)
We will put a protective canopy where is a sidewalk exists. There are really no projections from the building before debris to ricochet off of. The building is triangular shaped. There is an alley on one side a parking lot on another in the city street on the other. There is a extremely low volume of pedestrian traffic in the vicinity of the building.

RE: Temporary fence for falling debris

Unfortunately low volume is not no volume... FYI: We have had a recent spat of bricks falling off a building and used two layers of 19.7mm plywood, which showed itself able to withstand the hit in an on-site test the owner insisted upon.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources