72 kV Power Line Clearance to Above Grade Pipeline
72 kV Power Line Clearance to Above Grade Pipeline
(OP)
Hi all,
I am currently looking into CSA C22.3 No. 16-13 at tge moment. We have a pipeline running on Grade Level and in parallel to a 72kV transmission line (single circuit).
I would like to request anyone who have experience or seen similar installation and know what clearance was used. I wiill take that information in comparison to what I will obtain from my reading and interpreration of CSA C22.3 to gain some level of confidence that i understood it right.
Thanks,
I am currently looking into CSA C22.3 No. 16-13 at tge moment. We have a pipeline running on Grade Level and in parallel to a 72kV transmission line (single circuit).
I would like to request anyone who have experience or seen similar installation and know what clearance was used. I wiill take that information in comparison to what I will obtain from my reading and interpreration of CSA C22.3 to gain some level of confidence that i understood it right.
Thanks,