INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Fillet Weld WPS Qualification with Butt Weld

Fillet Weld WPS Qualification with Butt Weld

Fillet Weld WPS Qualification with Butt Weld

(OP)
Dear all,

I checked the API 1104 but couldnt find anything explains this directly. Normally in ASME Sec.IX when you ran a PQR with butt weld you are qualified to fillet welds also.

But in API 1104 in essential variables section code only states joint design like V to U bevel. Is there any other section that I missed explains this. Because its kinda extreme to make a specific WPS just for fillet.

Thanks.

RE: Fillet Weld WPS Qualification with Butt Weld

thandion,
It may seem extreme but that is what you have to do - see Clause 5.7 & 5.8.
Also reference 5.3.2.4 & 5.4.2.3,
Regards,
DD

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources