INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Development Length

Development Length

Development Length

(OP)
We are constructing pilecaps at site now which measures 1.6m x 5m x 1.3m deep and are each supported by 2 bored piles 800mm diameter. The piles are anchored 70mm from the base of the pilecap. The reinforcement of the piles are 12 pcs 25mm diameter epoxy coated bars and with 12mm spirals 80mm pitch. I have calculated the required development length in tension of 25mm to be 1.6 m. From the top of the pile, the 25 mm reinforcement can only extend at a maximum of 1.15m (juat a little below the 2nd layer top reinforcment of the pilecap. This is obviously not enough base on 1.6m which I have calculated.
In ACI 12.5 there is a 0.8 development length reduction factor for a 90 deg bend bar if stirrups are spaced not > 3db perpendicular to the bar being develop. I know this does not apply to our problem because the bars are straight vertically.
Is there any provision in ACI which states of a reduction in development length of straights bars in tension by enclosing them with ties? Thanks in advance

RE: Development Length

You can reduce the development length by the ratio Calculated Factored tension/ Allowable Factored tension.

ie actual stress divided by allowable stress

RE: Development Length

There is no provision which allows a reduction to tension development length (below a 1.0 factor) because the bars are enclosed by ties, since the basic values consider that bars are enclosed or have sufficient confining cover. You can get a reduction for compression bars if you use spirals meeting 12.3.3 (b)

RE: Development Length

I take it with the 5m pile cap length that you probably require some moment capacity and hence the reason for the tension reinforcement in the piles.

I don't work with ACI but I can't see how ties would provide development. For extra development you need either a cog or a head to the reinforcement. Not sure whether you can provide cogs with epoxy coated reo but that is what I would be looking to detail for this application.

RE: Development Length

If you need full tension capacity, I think you need hooks. What is the epoxy coating for?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources