×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Non correct Excavation

Non correct Excavation

Non correct Excavation

(OP)
Hi everybody

During the excavation for a mat foundation, we encountered a wrong excavation elevation by the surveyer for approximately 50% of the area. So, we recommended the contractor to continue the excavation with correct elevation until we solve the extra excavated area. The elevation difference is about 2.15m. Please any help.

RE: Non correct Excavation

(OP)
Hi

I forgot to include these:

1- should we fill the extra excavated area (about 2.5m) and then lay the mat.
2- should we design columns (of height 2.5m) under the mat in the area of the wrong elevation
or other options

RE: Non correct Excavation

“other options....” It seems to me that this foundation design and excavation project could benefit significantly by having some local, and real, engineering experience and judgement applied to it. If you find yourself in trouble while digging yourself into a hole, the first thing you should do is stop digging.

RE: Non correct Excavation

I would fill the hole with fill, or clsm

RE: Non correct Excavation

(OP)
Hi

Is the filling the best solution?

RE: Non correct Excavation

We cannot possibly solve your problem without knowing more about your site and your structure. Why does the building have a mat foundation? There is a likelihood that a mat foundation sited on two different materials, native soil at one end and fill at the other, will experience differential movement problems. Agree with dhengr...the decision is not simple, and needs evaluation by competent geotechnical and structural engineers.

RE: Non correct Excavation

Are you thinking that the design and construction of many short concrete columns and footings and redesigning of the mat is easier than laying down a bunch of compacted fill? I think dhengr provides the best advice on this one... sorry

RE: Non correct Excavation

(OP)
Hi

I wonder if there are other solutions.

RE: Non correct Excavation

How big is this mat foundation? To take care of the different support conditions you could always excavate the remaining area down to the "wrong" elevation then bring the entire area back up to the "right" elevation with compact structural fill.

I do agree with others, your best course of action is probably to find a local experienced engineer to help with the most economical solution. Since this is the surveyors/contractors mistake you could also put the burden of solving the problem on them, with the solution to be approved by you or another engineer.

RE: Non correct Excavation

Option #10: Dig the rest of the mat down to the incorrect elevation and pour a super thick mat.

Mike McCann
MMC Engineering

RE: Non correct Excavation

A common problem with "over excavation" is that it gets filled in improperly and structure settlement results. Generally that filling in is done by those on the job, sometimes trying to hide their mistake. Then the question of "why" takes time and expense. I sense a "can of worms" there.

RE: Non correct Excavation

2.15 meters is a lot. I would seriously consider replacing the contractor at this point.
columns are just a silly idea, you need to backfill
that fill could be in order of cost and suitability to handle heavy loads
a) structural concrete
b) lean concrete
c) very well compacted aggregate base course
d) and last but worst would be compacted native material

RE: Non correct Excavation

The solution depends on over-excavation geometry and soil nature. In a case we got irregular over-excavation in hard rock. We used back fill 24 MPa concrete to reshape to the original foundation level.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources