What should be in a construction work package to be given to a site engineer? Specifically around pipe work with equipment on a nuclear site.
Risk Assesment
Method Statement
Sign on sheet for achnoledgement of RA and MS
Isometrics
P & ID
Pipe support Design
Point of work risk assesment to be filled in by chargehand.
Am I missing anything else here?
Risk Assesment
Method Statement
Sign on sheet for achnoledgement of RA and MS
Isometrics
P & ID
Pipe support Design
Point of work risk assesment to be filled in by chargehand.