INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Is R-1 form required when bolting together U-2A components?

Is R-1 form required when bolting together U-2A components?

Is R-1 form required when bolting together U-2A components?

(OP)
One of our suppliers is claiming that the National Board requires all pressure vessel components to be tracked by issuing a R-1 form when you bolt together components from different manufacturers...despite the fact that each component has it's own U-2A form, and as such, was constructed in accordance with ASME Sec VIII, D1. I find no such Nat'l Bd requirement, so figured I'd ask the experts here.

[b]Background[/b]
Very often we order replacement parts for pressure vessels. For purposes of this thread, let's use a heat exchanger as an example. Let's say we order a replacement channel for a typical TEMA-AES heat exchanger. We have the component built to ASME Sec VIII, D1, and when the component arrives from the manufacturer, we bolt it up to the existing heat exchanger shell, perform a tightness (hydro) test at operating pressure, and then we place it in service. We do not contract the services or a repair organization (aka "R" stamp holder) to document the bolting together of these components, and as such, no R-1 form is ever issued. We've done it this way for as long as my plant has been in existence.

[b]Issue[/b]
Fast forward to now. Recently we ordered a new heat exchanger, and had two different manufacturers involved. One manufacturer made the channel/bundle assembly (a u-tube and integral channel assembly), and another manufacturer made the shell. The manufacturer of the channel/bundle assy followed all of the code requirements, conducted the necessary proof/hydrotest, and provided us with complete data package which included a U-2A (partial manuf data report) for the assembly. The channel/bundle assembly was then shipped to the other manufacturer....who simply bolted it up to the shell that they made. The shell manufacturer also provided a complete data package along with a U-2a form for the shell. However, they also issued an R-1 (repair) form and affixed a "repair" nameplate to this new heat exchanger simply because they bolted the components together. They are claiming that this was necessary to allow the National Board to track the components. We don't think the R-1 form, nor nameplate, were necessary. It just seems really odd for us to have brand new heat exchanger with a repair nameplate affixed...simply because one manufacturer decided it was necessary because they bolted together components from two different manufacturer's. The cynic in me thinks this manufacturer was quite happy to bill us more for this "repair"...but we don't think it was required, as the bolting together of components does not constitute a repair. What do you think?

Thanks in advance,
John

P.S. - I originally posted this in [i][color #A40000]Forums > Engineering Codes, Standards & Certifications > Engineering Codes, Standards & Certifications > ASME (mechanical) Code Issues Forum[/color][/i]. I tried to move it into this forum, but saw no way to do that, so I started a new thread here as I think this is the more appropriate forum for this questions.

RE: Is R-1 form required when bolting together U-2A components?

No, a Form R1 is not required.

RE: Is R-1 form required when bolting together U-2A components?

You are in the ASME requirements. When you have parts of diff. MFRS some one has to take responsibility for the complete assembly. A shop with the proper ASME authorization, stamp holder. If not done you will have to consult the jurisdiction as they are the ones authorizing the operation of the HX. I do not see why the NB gets involved. Its a news assembly not a repair. If not done as above then you have a non-code HX. Genblr.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources