which minimum thickness should be provided by jacketing of RC columns?
Do you still need to provide a bounding compound between the old and the new concrete?
lolobau
which minimum thickness should be provided by jacketing of RC columns?
Do you still need to provide a bounding compound between the old and the new concrete?
lolobau






RE: concrete column jacketing
As to bonding compound, I can't imagine how that would work. After applying the compound, the time elapsed to place the formwork would allow the compound to harden, thus resulting in a debonding layer rather than what you desired.
RE: concrete column jacketing
http://i.imgur.com/GZpQP.jpg
and it seams to me that jacketing would be the cheapest and easiest fixing
so the bonding compounds must be applied imediatly befor the casting?
RE: concrete column jacketing
RE: concrete column jacketing
Weld-Crete can be applied up to 10 days in advance, as a bonding agent if it's necessary.