Microsoft Project %complete and status date
Microsoft Project %complete and status date
(OP)
I am using MSProject 2010. I fail to update the project % complete to flush with the status date(in other words, the % complete up to status date). Photo attached showing % complete is updated to a day before status date. Anybody can help? Thanks.





RE: Microsoft Project %complete and status date
TTFN

FAQ731-376: Eng-Tips.com Forum Policies
Need help writing a question or understanding a reply? forum1529: Translation Assistance for Engineers
RE: Microsoft Project %complete and status date
Is that what you looking for?