Facility Up gradation Concept
Facility Up gradation Concept
(OP)
Hi All,
my company is going to up grade the existing facility and new separator is going to be installed in place of existing separator with higher capacity, the problem is being faced is relief line size which is increased to 12" from 6", a Gas flare sketch can be seen in attached file. please be remember no flare stack existing presently and both relief and excessive pressure both are going to BS&W pit.
I want to connect new 12" with 24" line after control valve, as we can't reduce the piping as per codes, can some one comment on this concept and suggest if some thing better I can do.
Thanks
10815l
my company is going to up grade the existing facility and new separator is going to be installed in place of existing separator with higher capacity, the problem is being faced is relief line size which is increased to 12" from 6", a Gas flare sketch can be seen in attached file. please be remember no flare stack existing presently and both relief and excessive pressure both are going to BS&W pit.
I want to connect new 12" with 24" line after control valve, as we can't reduce the piping as per codes, can some one comment on this concept and suggest if some thing better I can do.
Thanks
10815l





RE: Facility Up gradation Concept
I didn't understand your comment "can't reduce the piping as purr codes". Can you elaborate please.
My motto: Learn something new every day
Also: There's usually a good reason why everyone does it that way
RE: Facility Up gradation Concept
no flare stack existing and both psv and PCV outlet is going to burning pit, now we are upgrading our vessels with higher capacity, now PSV out size has increased to 12" and existing is 6" only.
my question was, does 12" line can joined with 24" PCV out line which 24"?
Thanks
10815l