Monolithic Curb and Conc Bus Pad
Monolithic Curb and Conc Bus Pad
(OP)
Hi All,
We have a project where the existing sidewalk at Bus Bay loading zone exceeds the 2% cross slope for ADA. I need to remove and replace both existing sidewalk and curbs. In order to meet the slope requirements, I have to adjust the curb height by one inch to to meet the slope requirements.
However, the existing curb was monolithically poured with the existing concrete bus pad. What is the possible solution to this without removing an entire concrete bus pad to minimize the cost?
We have a project where the existing sidewalk at Bus Bay loading zone exceeds the 2% cross slope for ADA. I need to remove and replace both existing sidewalk and curbs. In order to meet the slope requirements, I have to adjust the curb height by one inch to to meet the slope requirements.
However, the existing curb was monolithically poured with the existing concrete bus pad. What is the possible solution to this without removing an entire concrete bus pad to minimize the cost?





RE: Monolithic Curb and Conc Bus Pad
RE: Monolithic Curb and Conc Bus Pad
Will the dowels prevent the bus pad and new curb from separation or uplifting from each other?
RE: Monolithic Curb and Conc Bus Pad
RE: Monolithic Curb and Conc Bus Pad