×
INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Mortar lining inside welded steel pipe joint, smaller (less than 24-inches) pipes

Mortar lining inside welded steel pipe joint, smaller (less than 24-inches) pipes

Mortar lining inside welded steel pipe joint, smaller (less than 24-inches) pipes

(OP)
Our public water agency's construction specifications for mortar lined welded steel pipe (with gasketless welded joints, both full penetration butt welded and welded bell and spigot) require that the contractor fill the gap in the shop applied mortar lining of the two pipe segments (consistent with AWWA C-205, Section 4.7). Completing the interior mortar coating of joints in pipe greater than 24-inches is easy because they can be accessed manually from inside the pipe where the mortar is applied by trowel. Smaller pipe presents a practical problem. The method for completing the mortar inside the smaller pipe joint is to "butter" the inside of the joint, push the pipe ends together (seat the pipe if bell and spigot), and then pull a burlap wrapped ball through the joint which forces the mortar up into the joint creating a seamless mortar lining at the joint between the shop applied mortar lining of both pipe segments.

The practical problem is that there is always a need to weld the joint shortly after the pipe ends are mated, particularly when pushing the pipe through a casing which is a mostly continuous operation. The need to promptly weld the pipe ends is particularly important for full-penetration butt welded joints since the pipe ends are not stable until welded. Becuase the mortar in the "buttered" area inside the pipe will set before the weld can be completed, one cannot wait to mortar the joint until after the weld has been completed and cooled before pulling the ball to complete the mortared joint. If you pull the ball prior to welding, the mortar will seep up through the gap between the pipes and would need to be chipped or ground away from the gap which is to receive the full-penetration butt weld.

Has anyone had experience with completing the inside mortar on small diameter welded steel pipes? How have you done it? Have you tried rapid setting mortar on bell and spigot joints (so that the mortar can set quickly enough for the joint to be welded within, say an hour)? How long must one wait until the joint can be welded using a standard AWWA mortar mix? How can smaller butt welded joints be mortared at all? Any insight would be appreicated.

RE: Mortar lining inside welded steel pipe joint, smaller (less than 24-inches) pipes

I would consider changing the spec for pipe 24 inches or less to cement-lined Ductile. Or send the people that don't want to change into the pipe to apply mortar during the welding process.

Richard A. Cornelius, P.E.
WWW.amlinereast.com

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources