INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Bolt Traceability

Bolt Traceability

Bolt Traceability

(OP)
Hi All,

My company is transferring a Section VIII Div 1 design to production. It is a low pressure (50psig) and non-lethal service application. We have spec'ed out bolts that are SA-193-B7M. My question is regarding the traceability of these bolts. According to section 18 of the spec for SA-193, we have to order the bolts with MTR's. However, the material marking section (section 19) only requires that the bolts are marked with information to identify manufacturer and material grade, marking of the heat number is not required. My questions are:

1) Without any markings to tie the material to the MTR, how are we supposed to ensure traceability?
2) Section 19.3 of the SA-193 specification states that the manufacturer "is considered the organization that certifies the fastener was manufactured ... in accordance with the specification." Since there is nothing to tie the MTR to the bolts, are we limiting the scope of our inspection to ensuring that the MTR complies with chemical, mechanical and heat treatment specifications?
3) Is it required to trace specific heat numbers of bolts to final assembly or can we have a bin of accepted bolts of various heats and grab them as needed?
4) Am I overlooking something or are the requirements for traceability more lax for "off-the-shelf" components?

Please let me know if anything is not clear. Thanks for all the help!

Best,
Steris

RE: Bolt Traceability

In Section 18 of ASME SA 193 specification it clearly states that the manufacturer shall furnish a certification showing the test results for the fasteners or material and they were manufactured in accordance to this specification.

As you mentioned in Section 19 is the product marking or symbol applied to each stud. If you purchase a box or lot of studs, the tags or boxes will carry the appropriate symbol.

So, this means for fasteners or material supplied under this specification all you need to confirm for traceability is a certification from the supplier, and to ensure markings are correct when used and if you are dealing with boxes keep them segregated.

RE: Bolt Traceability

(OP)
Thanks for the clear response!!!

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources