one way slab with open ends
one way slab with open ends
(OP)
Has anyone designed a one way 4" slab with dimensions 3 meter by 6 meter that is fully anchored in the long span 6 meter side (to beams) but one of the short span 3 meter side open? One way slab means the long span side is attached to the beam by top bars and continuous lower bars.






RE: one way slab with open ends
BA
RE: one way slab with open ends
RE: one way slab with open ends
RE: one way slab with open ends
So for 100mm slab, it must be span in 2 directions or two-way.. meaning the long span of 6 meters and short span of 3 meters have to be both attached to the beams as in 2-way?
RE: one way slab with open ends