Level/Pressure Instrument connection to be provide block valve in between
Level/Pressure Instrument connection to be provide block valve in between
(OP)
Dear eng-tips member:
Sorry for bother you this trivia.
I am confused why the Level/Pressure Instrument connection to be provide block valve in between
Equipment nozzle and instrument tip point. (Pls see the attached)
Is it for maintenance issue or other reason? Why is the ball valve for the Temperature / Flow instrument usually not shown in the P&ID ?
Thank you very much for your help.





RE: Level/Pressure Instrument connection to be provide block valve in between
Often it is not just a single block valve. Double block and bleed arrangements are needed when the fluid is dangerous or under high pressure.
Best to you,
Goober Dave
Haven't see the forum policies? Do so now: Forum Policies
RE: Level/Pressure Instrument connection to be provide block valve in between
Flow elements don't have valves between them and the process because they are inserted INTO the process. You will have valves and bleeders up and downstream of the flow element to remove it if it fails, and those should be shown on the P&ID.