Management Change
Management Change
(OP)
Hi,
I'm dealing with three phase separators project.where pipings have been changed to B1 class from existing B2 class.
The change in piping class does have any complications or not.
Please advise me, shall I allow or cancel this change.
Thanks
10815l
I'm dealing with three phase separators project.where pipings have been changed to B1 class from existing B2 class.
The change in piping class does have any complications or not.
Please advise me, shall I allow or cancel this change.
Thanks
10815l





RE: Management Change
RE: Management Change
Normally, chemical engineer decides the service conditions. Material engineer or mechanical engineer decides the piping class. You need consulting with them.