INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Foundation Preparations Prior to Grouting

Foundation Preparations Prior to Grouting

Foundation Preparations Prior to Grouting

(OP)
Hi,

I have had to do a few inspections of concrete foundation pads that are to have pump skids (rotating equipment) grouted to them. The preparation has been done via bush hammering. I have looked in API 686 with regards to proper foundation preparation and I understand the general idea: remove laitence to expose aggregate rock. It also says to cover and protect the foundation if this prep work is completed months before the actual equipment is to be set.

However, I am interested in the details of foundation preparation and I was wondering if anyone knows of any spec or standard that addresses this in more detail.

I have attached a picture that shows preparation of a pad. From a quality perspective it is obvious that the left side was properly chipped and the aggregate is sufficiently exposed. The right side has been roughened with the bush hammer but is not as well done as the right side. Would you still consider this right side laitence? If so, I would think it is unacceptable.

I am interested in these details from a long-term quality perspective. I have heard from guys that have been in the business a long time that these foundational details can make the difference between say 15 and 30 years of life.

Any input would be greatly appreciated.

RE: Foundation Preparations Prior to Grouting

Either side looks perfectly fine to me. I prefer the right side, but even then, I think the preparation has been too robust. There is no laitance left, that is long gone. All that is really required is for the surface to be clean.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources