INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

How to show grouting on a P&ID

How to show grouting on a P&ID

How to show grouting on a P&ID

(OP)
Hello all,

This query is fairly non technical so should be simple if anyone has ever had the same issue before.

I'm preparing Rev C P&ID's for a project. Part of the destruct scope will not be done in the normal way of cut and remove because much of the pipework is underground. This underground pipework will be filled with grout.

I am unsure how to show the grouting work on the destruct P&Id's?

Also, how will the, now redundant, grouted lines show in the construct P&ID? I don't think I should take them off altogether because his may take them off the radar for future ground work in the area which is a hazard. At the same time leaving them on the P&ID will leave it very congested.

Any help much appreciated.

PR

RE: How to show grouting on a P&ID

I would not show grouting on a P&ID. At most, I'd put a note at the ends of the pipes on the project P&IDs, and then remove them from the permanent P&IDs when complete. Isn't there another scope document where this could go too, such as a "Description of the Work"?

Good luck,
Latexman

Need help writing a question or understanding a reply? forum1529: Translation Assistance for Engineers

RE: How to show grouting on a P&ID

I agree with Latexman. I have never noticed grouting being called out on a P&ID before.

RE: How to show grouting on a P&ID

(OP)
Thanks for the replies.

Something must show on the project P&ID's as these are live lines coming out of service. The question lies with the master update. I would only be comfortable taking them off the P&ID if they were captured alsewhere such as in civils drawings, reason being that if any excavation is done on the site the last thing anyone needs is to hit hard grouted pipe when digging!

PR.

RE: How to show grouting on a P&ID

They should remain on the UG drawings until permanently removed. That's where the "filled with grout" note needs to go.

Good luck,
Latexman

Need help writing a question or understanding a reply? forum1529: Translation Assistance for Engineers

RE: How to show grouting on a P&ID

OOS out of service should be placed on the drawing. With another note saying grout filled. That way If someone sees the line visually or on 3D drawings and go to p&ids they'll understand the situation.better

RE: How to show grouting on a P&ID

i am with Latexman on this. these should not be in the permanent P&ID's. they belong in underground civil drawings.

no one is going to be looking at P&ID's prior to digging in the future. they should be looking at the underground drawings. P&ID's don't show the "physical location" anyways.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources