Taping of 11kV transformer stator bar
Taping of 11kV transformer stator bar
(OP)
I have a situation where the failure of an 11kV transformer stator bar is being attributed to poor repair at a previous failure. Specifically it seems that the (repair) taping insulation was wound with a 10-20% overlay, instead of the manufacturer’s normal 50% overlay. I would appreciate any advice I could be given as follows.
1. Is it a cardinal rule that all insulation taping for high voltage applications should be carried out with a 50% overlay? If so, is there a specification for this or an authority that can be quoted.
2. Are compromised stator bars ever rehabilitated by manually retaping, or is it best to use new bars?
1. Is it a cardinal rule that all insulation taping for high voltage applications should be carried out with a 50% overlay? If so, is there a specification for this or an authority that can be quoted.
2. Are compromised stator bars ever rehabilitated by manually retaping, or is it best to use new bars?






RE: Taping of 11kV transformer stator bar
RE: Taping of 11kV transformer stator bar
RE: Taping of 11kV transformer stator bar
You can also see this specification does not allow butt lapped for groundwall insulation. I can speculate the reason is to maximize the distance that must be traveled to get through the insulation travelling along edges of tape rather than through the tape.
I also know that OEM's place a lot of attention to how the "seam" lines up between one layer and the next. If you overlay a half-lap layer on top of another half-lap layer where the seems line up, you line up the weak points of one layer with the next. I think it is preferred to stagger by 1/4 width between layers.
I'm inclined to think it is more important for B-stage than for VPI, but don't know for sure. If I was investigating a failure blamed on this, I'd be interested to know about the post-rewind electrical testing. If winding was bad from the beginning, how did it pass the ac factory test?
There are probably others more knowledgeable than me. If you don't get many responses here you may want to ask on the motors forum.
=====================================
(2B)+(2B)' ?
RE: Taping of 11kV transformer stator bar
http://books.google.com/books?id=4-Kkj53fWTIC&...
Above figure shows half-lapped and butt-lapped. So I used the term butt-lapped wrong in my post above. I should have used the term edge-lapped (instead of butt-lapped) in my post above... edge-lapped would involve some small overlap like 10-20-25%
=====================================
(2B)+(2B)' ?
RE: Taping of 11kV transformer stator bar
=====================================
(2B)+(2B)' ?
RE: Taping of 11kV transformer stator bar
A bit more detail might help. How big is this machine? Is the failure mode inter-strand, or bar-core in the slot, or even bar-bar in the endwinding region?
I have never seen a Roebel bar have inter-strand insulation repaired manually. I'm not even sure it would be possible even though the insulation demands are not high. Manual re-taping in the accessible endwinding region is not uncommon for machines where PD is a problem - this is usually done with the machine assembled as a 'patch' to keep the generator in service until a planned major outage when something more permanent can be arranged and budgeted for. The cost of a new bar is fairly small compared with the cost of removing a large generator and transporting it, then stripping it down. I wouldn't even consider re-taping a bar for an in-slot failure on a medium / large generator - it's too small an overall saving against a relatively large risk. 'Medium' for context being from about 20MW up to say 200MW.
RE: Taping of 11kV transformer stator bar
Thanks for your comments. I would be grateful if you could if IEC 60034 does apply. The machine is 11kV, 200MW. The failure was in-slot.
RE: Taping of 11kV transformer stator bar
Appreciate the detail of your reply. In your second post you refer to a figure, but when I click on the link I am taken to a Google page featuring a book, Handbook of Electric Motors, by Hamid A. Toliyat, Gerald B. Kliman. I may well buy the book, but this will take time, so could you attach the figure that you refer to.
RE: Taping of 11kV transformer stator bar
You might want to locate a copy of "Electrical Insulation for Rotating Machines." by Stone, Boulter, Culbert, and Dhirani. ISBN 0-471-44506-1, pub. 2004 by Institute of Electrical and Electronics Engineers. It's a very detailed reference and I found it highly informative.
The fact that it is a pretty big machine further reinforces my comment that a bar repair is not likely to be economic sense: with consideration to the cost of unthreading the rotor to allow access to the stator, plus the cost of downtime, the cost differential between a repair to the bar and a new replacement bar will be a small fraction of overall costs.
RE: Taping of 11kV transformer stator bar
Attached powerpoint slide 1 is figure from “Handbook of Electric Motors” by Toliyat, Kliman showing half-lap, butt-lap
Attached powerpoint slide 2, I created a powerpoint showing half-lap, butt-lap and edge-lap.
Edge lap is what you described in your orignal post.
=====================================
(2B)+(2B)' ?
RE: Taping of 11kV transformer stator bar