ColinPearson
Petroleum
- May 1, 2011
- 142
I've got a piece of equipment that I need to suspend from a spring hanger that pins to lugs on an existing W12x53. The beams that frame in one end of this W12 conflict with the equipment during installation, so I am proposing to remove them and install a temporary beam directly above and parallel with this W12. The W12 top flange of the W12 would then be welded to the bottom flange of the temp beam.
I am somewhat familiar with prying calculations and familiar with local flange yielding due to point loads on a flange (as from a beam trolley). However, I do not know how to deal with local flange yielding in this situation.
Any thoughts on the matter folks?
Particulars are:
-W12x53 @ 39" long, A992, spring hanger lug at the midspan
-About 45 kip load
-The way the flanges are coped to frame into other steel, I can get 17" of weld along each side. The weld group is plenty good for the load. (Flange on the W12 is 0.575" so a sizable fillet is possible, though not necessary).
THANKS!!!
I am somewhat familiar with prying calculations and familiar with local flange yielding due to point loads on a flange (as from a beam trolley). However, I do not know how to deal with local flange yielding in this situation.
Any thoughts on the matter folks?
Particulars are:
-W12x53 @ 39" long, A992, spring hanger lug at the midspan
-About 45 kip load
-The way the flanges are coped to frame into other steel, I can get 17" of weld along each side. The weld group is plenty good for the load. (Flange on the W12 is 0.575" so a sizable fillet is possible, though not necessary).
THANKS!!!