INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Calculating Applied Loads for Pile Design

Calculating Applied Loads for Pile Design

Calculating Applied Loads for Pile Design

(OP)
Hello all,
I'm a structural engineer and so I don't often design the actual piles to support my builidngs, I do however get asked to provide reactions so the Geotechnical Engineer can design them. My question is how exactly are the applied loads to be calculated for desing of these piles based on Canadian design practices, I'm talking specifically the vertical loads applied to the piles.

I know that unfactored loads can be used and so until now we have been using the simple formula of P = aD + bL + cS +dW, where a = b = c = d = 1. However, on occasion the results of this formula is nearly equal to or greater than the factored loads, which doesnt seem right. Is there documentation somewhere that allows us to use combinations to reduce the live, snow and/or wind loads? Or are we in fact not being as over-conservative as I think?

Cheers,
Devan

RE: Calculating Applied Loads for Pile Design

I wouldn't waste any time trying to refine pile loads. I would figure out load per pile using your formula, add a fudge factor and round up to the nearest 10 tons.
With any subgrade design element, it's disastrous to be caught short. It's just too difficult to get more capacity once piles are in the ground. You'll sleep better if you're way conservative.

RE: Calculating Applied Loads for Pile Design

Agreed with Jed if YOU are designing the piles. If you're just passing along values to your geotech, just give your working loads - let them do the fudge-factoring.

In Russia building design you!

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources