Need to manualy change percent complete
Need to manualy change percent complete
(OP)
Hello,
I need to manualy change percent complete, and be able to change a proposed finish date without changing the percent complete. Make sense? :). What columns should I use for the finish date? I'm new to project but I can't find any info on this. When you change the finish date, the percent complete changes, and I need it to remain constant.
Thanks,
Joe
I need to manualy change percent complete, and be able to change a proposed finish date without changing the percent complete. Make sense? :). What columns should I use for the finish date? I'm new to project but I can't find any info on this. When you change the finish date, the percent complete changes, and I need it to remain constant.
Thanks,
Joe





RE: Need to manualy change percent complete
You should be able to simply manually enter the percent complete directly in the that column and the dates should stay put.
TTFN
RE: Need to manualy change percent complete
But careful. If the advance percentage is lower than the one you should have accomplished by status date, then when you do the "schedule update" command, the activity will be reprogrammed and "finish date" will move forward.