INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Restraint to thermal cracking from piles (or columns)

Restraint to thermal cracking from piles (or columns)

Restraint to thermal cracking from piles (or columns)

(OP)
We're designing a piled tank for a sewage treatment works to Eurocode 2. The slab needs to be water retaining so thermal cracking is an important consideration.

Can anyone offer any advice on how to estimate the restraint factor (R) due to the piles?

I have come across 2 methods:
  • Work out the strain and shrinkage due to the temperature drop, then the stress, then the tensile force in the slab. Apply this force to the top of a pile and work out the deflection (assume horizontal spring stiffness=vertical spring stiffness). Plot two lines on a graph at R=0 and R=1 and where they cross is the restraint factor. This is the method suggested in CIRIA C660 based on a suspended slab between two walls - example attached.
  • Work out the strain and shrinkage due to the temperature drop for 2 span sizes (not obvious how these spans are derived), calculate the force on a pile needed to create this deflection, use this force to work out the restrained stress in the slab, then the restrained strain in the slab and divide this by the strain with no restraint to get the restraint factor. (This is the example given in some course notes I have but I can't see where some of the numbers have come from).
However both methods give very small restraint factors (less than 0.05 for piles) however the second method says 'use 0.2' at the end of the calcualtion with no further explanation. The CIRIA report says that piled slabs should be designed as if they are end restrained, which suggests that the restraint is significant.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources