Is there any standard or best practices stated that we must first energize the upstream system then the downstream system.
example : for a transformer (150kV / 6 kV) feed a 6 kV Busbar. The busbar feed 3 Dry transformers (6kV/400V). We must first energize the 150kV Transformer, then busbar, and the last one to energize is dry transformer.
Sorry for my english..
example : for a transformer (150kV / 6 kV) feed a 6 kV Busbar. The busbar feed 3 Dry transformers (6kV/400V). We must first energize the 150kV Transformer, then busbar, and the last one to energize is dry transformer.