INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Standard for energize upstream first

Standard for energize upstream first

Standard for energize upstream first

(OP)
Is there any standard or best practices stated that we must first energize the upstream system then the downstream system.
example : for a transformer (150kV / 6 kV) feed a 6 kV Busbar. The busbar feed 3 Dry transformers (6kV/400V). We must first energize the 150kV Transformer, then busbar, and the last one to energize is dry transformer.
Sorry for my english..

RE: Standard for energize upstream first

Well, if it is a radial system you can't energize it in the opposite order...

I'm not sure what you are trying to get.

RE: Standard for energize upstream first

(OP)
Yes it is a radial system. sorry for my english but my point is, Standard Operating Procedure always says that we have to energize (Close CB) on Primary of transformer ( supply side) first then the secondary (load side). is there any standard or recommended practice related to this point. Or we can do the opposite way by connected all the load first then energize the transformer.
thank you

RE: Standard for energize upstream first

Are you having inrush problems?

RE: Standard for energize upstream first

No standard that I am aware of, just good engineering practice to energize from source to load and denergize from load to source.

RE: Standard for energize upstream first

Energizing "smaller" portions at a time is more typical than energizing all of it at once. There are circumstances such as transmission line re-closing that could result in energizing an entire large block of load. Be aware of inrush/cold load pickup if you do energize everything at once. Also, energizing small portions at a time allows you a chance to verify each portion is working correctly.

RE: Standard for energize upstream first

If the load on the feeder is a substantial portion of the generating capacity it may not be possible to block load the entire load.

Bill
--------------------
"Why not the best?"
Jimmy Carter

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources