INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

canopy CFS

canopy CFS

canopy CFS

(OP)
Hello All,
We are designing a Canopy using Cold Formed Steel.As we want to create a long span,as a general experience how long CFS members can span? I found 16" member as deepest size studs and planning to make a box section by attaching two members toe to toe and spanning about 30 ft unbraced length.
Does this sound resonable? Any thoughts/experience appreciated.

RE: canopy CFS

Typical PEMB have cold formed purlins spanning about 20'-25' so it sounds reasonable. If you're going to double up your steel studs wouldn't it be easier to connect them together toes out? Might not be as strong as the box section, but 2 - 16" members should be able to span 30'

RE: canopy CFS

(OP)
This member has 8 ft tributory of 45 psf wind uplift load (it's a major beam/girder).As unbraced length of 30 ft gives very little capacity being long unbraced length. I am assuming toe to toe connection makes it a tube member and avoid torsional buckling giving almost full member flexural capacity.
But I don't know how to check it-Is there a spreadsheet or something available to calculate the member capacity of such sections.

RE: canopy CFS

McGill -

We use LGbeamer in our office to design CFS members. You may want to check that. Good Luck!

RE: canopy CFS

Not a good idea to rely on a spreadsheet to do something which you do not know how to check.

BA

RE: canopy CFS

I would connect them web to web - much easier. What ever you do, make sure you use 2 members per rafter. At these spans and depths, CFS members are really unstable. It actually sounds like pre-engineered trusses would be better or even red-iron. If it wasn't for the steel erectors raping the GC, red iron would be used more often in these situations.

RE: canopy CFS

The manufacturer of the CFS members will have all of the section properties you need...you can build your own spreadsheet from there. The cold-formed steel code is a pain in the ass but still fairly straight forward.

How do you intend to connect toe to toe? The only thing I can think of is wrapping the members with sheet metal every couple of feet.

RE: canopy CFS

AISIWIN is a free download and will do this analysis for you.

RE: canopy CFS

30' unbraced in light gauge purlins? Did you forget the bridging?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources