INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Eccentrically loaded joints

Eccentrically loaded joints

Eccentrically loaded joints

(OP)

Hello,

Assume the fasteners subjected to eccentric load, where by theory the force on each fastener is proportional to it's distance from the centroid of the fastener group. For the joints, which carry no moment it is generally assumed that each fastener is equally loaded. In case of eccentric load it is unlikely that critical fastener will deform as much as the low loaded fasteners, but the traditional vector analysis is known as conservative. What recommendation do you have for design if the joint is statically loaded and on some fasteners the allowable load is exceeded? Can the loads on the neighboring fasteners be averaged? Thanks for your opinions.

RE: Eccentrically loaded joints

first, a couple points about your post ...
"it is unlikely that critical fastener will deform as much as the low loaded fasteners" ... the idea behind load proportional to distance is that bolts will strain proportional to distance, therefore more highly loaded bolts are expected to strain more.

i think you can do something about load redistribution, about fasteners becoming plastic and so more flexible compared to elastic bolts. i think it's somewhat reasonable to imagine that the bolt group won't Fail untill all the fasteners are working at their ultimate allowable. i think it'll become a messy calc ...
apply your elastic dist'n untill one bolt reaches it's allowable, say 80% of the required load
delete the critical fastener from the load calc, essentially limiting it to it's allowable, then re-do fastener loading to balance the new pattern about the old CG, apply maybe 5% load or untill the next fastener reaches it's allowable,
and so on !

it might be easier to say each fastener can carry it's ultimate allowable, acting in generalised directions (each fastener reacts Pult in direction "alpha", which varies with each fastener, yes?), so that the fastener forces balance P and P*d (where d is the off-set in your design, to say the bolt group elastic CG) so you'd get to ultimte allowable "P" for the joint.

this approach is probably optimistic, you might consider the effect if the critical bolt fails.

clear as mud ?

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources