INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Non code pressure vessel to to code conversion?

Non code pressure vessel to to code conversion?

Non code pressure vessel to to code conversion?

(OP)
Is it possible, under any scenario, for a vessel that was not designed and fabricated to BPVC VIII to be converted and stamped per code? If so, what would be the process?

RE: Non code pressure vessel to to code conversion?

Unlikely. There are a significant number of in-process QA procedures that need to be followed. Inability to demonstrate them will likely make the process untenable.

RE: Non code pressure vessel to to code conversion?

Agreed, plus calcs, drawings, etc.

And good luck finding an AI willing to out on that limb...

Regards,

Mike

RE: Non code pressure vessel to to code conversion?

Absolutely agree. You cannot go back and attempt to code stamp a vessel without having proper documentation regarding design and fabrication history, along with no involvement from an AI.

Now, you can do an evaluation and show compliance with ASME code design, and convince a regulatory body to accept the vessel as a state special or request a variance.

RE: Non code pressure vessel to to code conversion?

MTR and NDE records must be signed by AI, as well as witness of the hydrotest, that will put the task very difficult. But I believe you can re-hydrotest and witness by AI.

RE: Non code pressure vessel to to code conversion?

I presume there's no provision for a 4x proof test on the thing in lieu of the calcs and QA, assuming conditions and size make success likely. If you're after a code MAWP/relief pressure of 25 psig and the thing has a calculated MAWP of 100 psig assuming the construction was done correctly, such a provision might come in handy if it exists. I know that this is sometimes accepted by local AIs for pressure piping components which don't have well established MAWP limits.

RE: Non code pressure vessel to to code conversion?

As an AI, ain't gonna happen!

RE: Non code pressure vessel to to code conversion?

If you have the vessel itself, but don't have documentation of the building of it, you have no way of knowing whether the welding itself met ASME or not, among other things.

Some non-code vessels will use heads that are also non-code, typically with too small of a knuckle radius, and that can't be corrected.

RE: Non code pressure vessel to to code conversion?

I have a similar question:
If the vessel WAS designed and fabricated to BPVC III, but not tested, is it possible to test the vessel to obtain a U-Stamp in a state that is not governed by the NB (Wyoming)?

RE: Non code pressure vessel to to code conversion?

dentonous - if ALL of the in-process fabrication and inspection were done in accordance with the Code (including appropriate witnessing by the AI), and the ONLY thing missing was the final hydro (or witnessing of the final hydro), then it may be possible. Contact your AI for guidance.

RE: Non code pressure vessel to to code conversion?

If you are the Purchaser of the vessel and wish to U-Stamp it, the vessel would have to be made to the Code and thePurchaser's ASME Quality Manual. It is highly doubtful that the Purchaser can do so even if it has a U Certificate from the ASME; furthermore, why would the Purchaser want to assume the liability?

If you are the Manufacturer, it may be possible provided you can confirm that the vessel was designed and fabricated to the Code and in accordance with your Quality Manual subject to AI acceptance.

RE: Non code pressure vessel to to code conversion?

I think Metengr is exactly right. Once the vessel has been fabricated (completed), the only option is to perform evaluation documenting the vessel meets Code requirements and seek a State Special or Variance from the Jurisdiction where vessel is installed. If you were in a non-code jurisdiction, the vessel owner should seek guidance of his boiler & machinery insurance carrier.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members!


Resources