exceeding top concrete cover
exceeding top concrete cover
(OP)
what will you do if found pedestal with top concrete cover say about 120 mm (while the design state that concrete cover 50mm) ? This condition raise after do core drill to take a sample..






RE: exceeding top concrete cover
RE: exceeding top concrete cover
note that concrete already pass 28 days..
RE: exceeding top concrete cover