INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Piping Codes for steel plant

Piping Codes for steel plant

Piping Codes for steel plant

(OP)
Dear Folks:

I am going to begin the design of steel plant, so I need to define the codes for apply.

Do you know what piping codes can I apply for design?

ASME B31.1 Power Plant, motion fluid, generally for electric generation, like steam.
ASME B31.3 Process Piping. Is there some place of steel plant that I can use this kind of code? It covers Oil&Gas, Petrochemical.
ASME B31.9 Building services, This code can apply for services like air, dry air, utility water, demin water, cooling water, argon, O2, pure water, Nitrogen gas, when conditions don't exceed rating #150.

For ducts, services like Blast Furnace Gas, Coke oven gas and converter gas; iis it possible to use SMACNA-ANSI, for industrial application?

there some other services that I can't classify inside of these codes, like: LPG Gas from city, Hydraulic oil, grease.

All of these assumptios are correct? Please your feedback with this.

thanks for the support

B. Regards,

Luis Felipe

RE: Piping Codes for steel plant

You should approach local / national authorities and the plant owner to determine which codes to apply to design engineering. It's probably not your job to decide this.

I don't know of anything specific to steel production so I would reconmmend ASME B31.1 / B31.3, ASME VIII Div 2 and similar.

RE: Piping Codes for steel plant

You should refer to Project specifications provided by your respective client. Within the same, you will find all required codes w.r.t to your design: "ex. piping specification, material selection phylosophy....etc"

All project documents shall be provided to Contractors/Subcontractors as a complete package during bidding/tendering stage. Thus you shall strictly follow the same.

RE: Piping Codes for steel plant

The Owner should define the standard to be used for the plant in the absence of any legislative requirement. ASME B31.3 would be apt as the steel plant involves similar piping/risks etc of a chemical plant.

“The beautiful thing about learning is that no one can take it away from you.”
---B.B. King
http://waterhammer.hopout.com.au/

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.